LG orders G10 Lithography tool
Of course these estimates are for 60” TVs at 100% yield, and will be discounted, especially as the plant ramps production, but it gives investors the understanding of the capabilities and capacity of these tools. That said, the typical lead time for backplane lith tools is between 14 and 18 months, although the size modified units might take a bit longer. If LG placed the order in February, the expected delivery date would be between April and August 2018. Our timeline for this fab has been phase 1 of the project scheduled for June 2018 which is a bit optimistic relative to the tools construction time, but still within reasonable parameters. While Nikon is hard-pressed to meet its delivery schedules as it is, the fact that this will likely be the largest lith tool ever built (and likely the most expensive) in the display space, they might have the incentive to speed up the process. Perhaps LGD has also given them some financial incentives to bring the tool in more quickly?