However, as it is rare that plans, especially for such a large project, meet early timelines, Samsung’s construction has been slower than expected and the plant 1 start up date was pushed back again to 2026 as construction has been on hold for the last few months a result of a weak semiconductor market. This has caused the Taylor city government to amend its original tax incentive plans, which were a bit open ended, to push Samsung more intensely to move forward with the project. Taylor made the following changes to the plan:
- Samsung will start bringing in process equipment by the end of 2026
- Taylor capped its reimbursements to Samsung for plan reviews and inspections at $9m, down from $25m previously.
- Samsung must complete 6m ft2 of permanent and temporary building space by the end of 2026 and another 1m ft2 by 2028.